Building a Soil-Based Wastewater Treatment System: 16 Months of Construction Steps

日本語版: 排水浄化システムの施工手順|掘削から炭・石・マルチングまで16か月の記録

Once a wastewater treatment system is finished, all you see is a few pipes and a layer of mulch. The layers underneath, and the order in which they were placed, are only visible during construction.

This article records, step by step, how EKAM built its own electricity-free wastewater treatment system on company land, from excavation in January 2025 to first use in May 2026: about 16 months of site photos. We show how the anaerobic, aerobic and soil zones explained in part one take physical shape.

For each step we note the materials and why we chose them. We hope it is useful not only to people building something similar, but to anyone working with water and air below ground, from drainage improvement with charcoal and stone to rainwater infiltration.

Construction Overview

Period Work Main materials
Jan 2025 Setting out and trench excavation Excavator, stakes, batter boards
Feb–Mar 2025 Checking drainage; foundation for the anaerobic chamber Charcoal, rubble stone, single-size crushed stone
Apr–May 2025 Leveling; floor and edging; brick side walls and vent pipes; charcoal backfill Gravel, natural hydraulic lime, brick, jute, perforated pipe, charcoal
Dec 2025 Round stones as the chamber lid; inspection box Flat round stones, concrete box
Jan 2026 Split-stone cover, microbial habitat (filter media), deep vertical holes Split stone, roof tiles, foamed glass media, PVC pipe
Feb 2026 Infiltration pit, overflow pipe, house connection Rubble stone, charcoal, perforated pipe
Apr–May 2026 Covering and mulching; first use Coir, jute, plant mats, leaf litter, leaf mold

There is a gap between May and December 2025. You do not have to build it all at once; you can check each layer before moving on, which is one of the strengths of this method.

Steps 1–3: Excavation and the Base

Step 1. Set out and dig the trench (January 2025)

We set out the position and levels with stakes and batter boards, then dug the trench with a small excavator. The base level was worked back from the height and fall of the drain pipe so that wastewater flows in by gravity.

Setting out with stakes and batter boards and digging the trench with an excavator
Setting out with stakes and batter boards and digging the trench with an excavator

While digging, we read the color and hardness of the trench walls. Below the topsoil was red native soil mixed with rock.

Step 2. Watch how water soaks in (February 2025)

Water collected in the open trench and was slow to drain, telling us the clay-rich ground accepts water slowly. This confirmed our approach: deliberately build pathways for water and air at the base and around the structure.

Water pooled in the excavated trench; clay-rich ground drains slowly
Water pooled in the excavated trench; clay-rich ground drains slowly

Step 3. Building the foundation for the anaerobic chamber (March 2025)

We laid charcoal along both edges of the trench floor, set rubble stones on edge across the floor, then spread crushed stone over the whole base. The charcoal bands protect the sticky clay soil. The rubble stones and crushed stone carry the load above while letting water escape.

Charcoal laid along both edges of the trench floor. The clay was so sticky that it turned to mud underfoot whenever it rained
Charcoal laid along both edges of the trench floor. The clay was so sticky that it turned to mud underfoot whenever it rained
Rubble stones set on edge, covered with single-size crushed stone. It carries the load while leaving plenty of voids, so it does not block infiltration
Rubble stones set on edge, covered with single-size crushed stone. It carries the load while leaving plenty of voids, so it does not block infiltration

Steps 4–6: Building the Anaerobic Chamber

Step 4. Level the bed (April 2025)

We set formwork and spread fine gravel to a level bed. If the floor level varies, water collects on one side and part of the system is overloaded. Keeping a long run level is the basis for even performance.

Formwork set and fine gravel leveled for the chamber floor
Formwork set and fine gravel leveled for the chamber floor

Step 5. Floor and edging (May 2025)

We poured a floor of natural hydraulic lime (NHL) and laid the bottom course of brick along both edges. This is the floor of the anaerobic chamber, which holds incoming solids.

Natural hydraulic lime (NHL) floor with brick edging along both sides
Natural hydraulic lime (NHL) floor with brick edging along both sides

Step 6. Side walls, pipes and charcoal backfill (May 2025)

We built the side walls four courses of brick high and ran jute-wrapped perforated pipes (vent pipes) along both outer sides. The space around the chamber was backfilled with charcoal and tamped repeatedly. Charcoal keeps its internal pores even when compacted, creating a wall that is firm yet able to breathe.

Jute-wrapped vent pipes (perforated pipes) along both sides of the chamber walls
Jute-wrapped vent pipes (perforated pipes) along both sides of the chamber walls
The end of the chamber, with jute-wrapped vent pipe connections and a PVC riser
The end of the chamber, with jute-wrapped vent pipe connections and a PVC riser

Steps 7–9: The Aerobic Layer and Vertical Holes

Step 7. Round stones and an inspection box (December 2025)

We laid flat rounded stones as the lid of the chamber. The large gaps between them let clarified water and air pass, and biofilms form on the stone surfaces too. A concrete inspection box was set partway along so we can check conditions later.

A concrete inspection box set within the brick-edged chamber
A concrete inspection box set within the brick-edged chamber
Flat round stones laid as the chamber lid; water and air pass through the gaps
Flat round stones laid as the chamber lid; water and air pass through the gaps

Step 8. Split-stone cover and a home for microbes (January 2026)

We covered the round stones with split stones, framed both sides with timber and roof tiles, and filled with foamed glass media as a home for microbes. The split stones act as a lid, stopping soil and fine particles from entering the anaerobic chamber. The tile edging keeps the filter media and the surrounding charcoal from mixing.

Split stones covering the round stones, framed with timber and roof-tile edging
Split stones covering the round stones, framed with timber and roof-tile edging
Foamed glass media over the split stones as a home for microbes, with black charcoal outside
Foamed glass media over the split stones as a home for microbes, with black charcoal outside

Step 9. Deep vertical holes downstream (January 2026)

At the downstream end we dug deep vertical holes and connected them to the system with pipes, to take overflow during heavy rain. The aim is to spread water three-dimensionally instead of collecting it in one place.

A deep vertical hole downstream that takes overflow in heavy rain and spreads it into deeper soil
A deep vertical hole downstream that takes overflow in heavy rain and spreads it into deeper soil

Steps 10–12: Infiltration Pit and Preparing for Backfill

Step 10. Rubble stone and charcoal in the infiltration pit (February 2026)

In a separate square pit we packed rubble stone and topped it with fine stone mixed with charcoal. The voids hold water temporarily and release it slowly into the surrounding soil.

Rubble stone packed into a square pit
Rubble stone packed into a square pit
Fine stone mixed with charcoal over the rubble stone
Fine stone mixed with charcoal over the rubble stone

Step 11. An overflow pipe (February 2026)

We installed a perforated overflow pipe above the microbial chamber, because a sudden rise in water volume during heavy rain would otherwise not drain properly. The drain from the house was connected at this stage.

The perforated overflow pipe installed above the microbial chamber
The perforated overflow pipe installed above the microbial chamber

Step 12. Coir, jute, plant mats, leaves and leaf mold (April–May 2026)

We covered the pipe and filter media with coir and jute, laid plant mats over them, and spread a thick layer of leaves and leaf mold as the base for backfilling. The covering stops soil from falling into the layers below; the leaves and leaf mold prevent rain from sealing the surface. All of it will decompose into topsoil. Soil was then backfilled on top, and the system came into use in May 2026.

Covering the pipe with coir and jute
Covering the pipe with coir and jute
Plant mats (taken from plants whose roots had formed a mat on concrete or asphalt) laid over the covering, with vent and inspection pipes
Plant mats (taken from plants whose roots had formed a mat on concrete or asphalt) laid over the covering, with vent and inspection pipes
The base for backfilling is complete; soil goes on top next. Once finished, only pipes and mulch are visible from above
The base for backfilling is complete; soil goes on top next. Once finished, only pipes and mulch are visible from above

Key Points for Construction

  • Floor level and fall: work back from the drain pipe and keep long runs level to avoid overloading one section
  • Keep layers separate: round stone, split stone, foamed glass media and charcoal each have a role; protect the boundaries with jute, plant fiber and roof tiles
  • Tamp the charcoal: loose charcoal settles, and it keeps its pores even when compacted
  • Leave inspection windows: inspection boxes and risers let you check water level and odor later
  • Avoid digging in the rainy season: rain in an open trench weakens the walls and damages the base

In Japan, facilities that treat toilet waste fall under the Johkasou Act. If you are considering a similar system, consult your local authorities before you build. We cover the regulatory side in part one.

Frequently Asked Questions

Q. How long did it take to build the wastewater treatment system?
Our self-build took about 16 months, from excavation in January 2025 to first use in May 2026, with pauses to check conditions along the way. Highly permeable soil, ready-made concrete products or continuous work would shorten it, but the method does not require building everything at once.

Q. What should you watch for when backfilling with charcoal?
Tamp it repeatedly. Loose charcoal settles later, but charcoal keeps its internal pores even when compacted, so the backfill stays firm while keeping air pathways open.

Q. Why cover round stones with split stones?
The split stones act as a lid that stops soil and fine particles from passing through the gaps between the round stones into the anaerobic chamber. The space above is home to aerobic microbes, so filter media and a covering layer are placed over the split stones to form the aerobic chamber.

Q. Which step requires the most precision?
The floor level of the chamber. If the level varies, water collects on one side and part of the system is overloaded. Work back from the height and fall of the drain pipe and keep long runs level.

Conclusion

  • We built the system in stages: excavation, base, anaerobic chamber, aerobic layer, infiltration and distribution, then covering and mulch
  • The key is layering materials with different roles and protecting the boundaries between them
  • Level accuracy, tamped charcoal and inspection access are hard to fix later, so do them carefully from the start
  • The method allows pauses between stages to check each layer

Can the same idea support a guesthouse or restaurant? We answer that in this article.